Renovations:
Removed the siding from the East Wall and got ready to dig the footings.
Footings are poured for the new Parlour.
Flooring built for the new Parlour.
Removed the front entrance and had holes dug for footings.
Walls and roof trusses for Parlour are up. New windows on 2nd Floor installed.
Inside the new Parlour.
Roof shingled on new Parlour and framing finished for new Entrance.
Pouring the concrete for the new front entry.
Windows installed in the new Parlour. Roof on the East entrance and the door installed.
Front addition framed and covered in. Ready for the roof.
The roof being covered in on the new front addition.
Roof shingled and windows installed on the new front addition.
Building the sound room in the new East entrance.
Framing the new hallway from the new parlour to the kitchen.
Framing the entry, office, utility room and the washroom in the new front addition.
Siding sorted and ready to put on.
Siding put on the new front addition.
Carrying beam installed.
"Rub-A-Dub-Dub" Four men in a tub!
The old walls removed and the new framing done for the choir area.
Forming the walkway so the concrete can be poured for the front and side entrance.
The platform is finished for the choir.
Siding is nearly finished on the East addition.
Siding is finished on the east entrance and concrete walkways done.
Straping put on the ceiling in the new parlor.
Getting started on the kitchen. Dishwasher and stoves put in place.
Building up the soil around the foundation.
Adding new gravel to build up the parking lot.
Electrician is beginning to wire the building.
Working on the wiring.
Continuing to work on the plumbing.
Gyproc finished in the family washroom.
Beginning to install the heat pumps.
Installing heat pumps.
Insulating the east entrance.
Insulating and putting on the vapor barrier. We now have heat in the building.
Flooring and toilet installed in the family washroom.
Shingeling the north side of the roof.
Shingeling finished.
New windows installed in the kitchen.
Gyproc put on the parlor ceiling.
Parlor finished!
Kitchen gyproc finished and opening cut in the wall for serving.
Front entrance gyproc finished!
Gyproc finished, starting to crackfill the kitchen.
Installing doors.
David sanding the kitchen cabinets, getting ready to paint.
Putting decorative trim on the baptistry.
Kitchen cabinets installed and almost ready to paint.
Choir Room crackfilled.
Dave crackfilling the choir room.
Charlie painting in the kitchen.
South hallway painted. Cabinets installed.
Stan painting the Sanctuary.
The front entrance painted.
Kitchen cabinets painted and the hinges and handles put on.